Choose a Pilot Site Whose Results You Can Explain
Look for a site with material boiler fuel use and enough operating information to explain a result. A club with accessible plant records, available gas readings, and a facilities team that understands how the boilers run gives the project a practical starting point. Check which services rely on those boilers. A leisure site might supply pool heat and hot water for showers from one system, while another runs separate equipment for some of those loads. Floor area and membership numbers give limited insight into those differences.
Decide what the test site shares with the rest of the estate. The David Lloyd case study describes heating and hot water primarily supplied by combined heat and power units and Hoval Euro SR 900 kW boilers. It also notes facilities such as pools and indoor courts. The portfolio team needs enough detail to understand where a similar arrangement exists and where the boilers have a different role. A site can be a worthwhile project in its own right and still offer limited evidence for a different type of plant. Heating equipment in the David Lloyd case study
Before selecting the pilot, ask the local team what will change during the prospective test. A pool closure or a change in opening hours could significantly alter the load. If a site has other heating work planned, identify those measures and dates early. This helps the estates team choose what it can measure and whether the first site will answer questions about boiler behaviour, the value of the combined project or both.
Separate the Findings by What Was Measured
Optiburner is a retrofit that changes the timing of burner firing in a commercial boiler. The heating circuit retains heat after a burner stops. Where conditions allow, the control extends the interval before the next firing so the boiler can use less fuel while meeting demand. The product compares burner operation with optimisation engaged and disengaged and makes the results available in a downloadable Savings Report. That record gives the project team a way to examine how the equipment responded under the conditions tested.
Optiburner boiler optimiser
In the David Lloyd case study, Optiburner’s comparison showed 31% fewer boiler firings over 24 hours. The figure describes burner starts during a short test period. Run times help explain what those starts mean for the boiler, because burns can last longer even when they occur less often. The case study also describes a short-term Savings Report. A portfolio team reviewing the evidence can ask how many cycles the report covers, when the comparison was made and what the plant was serving during that time.
For an estate planning its own trial, agree how burner information will sit alongside metered fuel use. If a dedicated meter serves the boilers in the trial, document that scope. Where the meter also covers other gas equipment, check what separate readings are available. Record the conditions the boilers were operating under and note changes to opening hours, services or plant during the review. A trial with a clear measurement boundary gives the team a better basis for deciding how much of the result it can use in a budget.
Account for Insulation in the Project Results
The David Lloyd project included ValveWrap insulation on approximately 50–60 large fittings at each site. The case study attributes an additional 2–3% energy savings to the insulation and reports approximately 17% overall energy savings from the two measures at sites where testing was feasible. The project therefore includes changes to burner operation and changes to heat loss at the fittings. Those figures have different scopes from the 31% reduction in firings.
For another estate, document which fittings were insulated and on what dates, along with the dates and boilers covered by the optimiser installation. Decide whether the next set of sites will receive both measures or whether some already have insulated fittings. A property with existing insulation may still be a candidate for boiler optimisation. The available heat loss reduction and the cost of the work will differ from those at a site where both measures are being considered.
The case study reports £305,000 in total utility bill savings for the wider project. It covers a programme that included both measures. If another club is considering boiler optimisation alone, prepare its forecast based on that club’s relevant fuel use, tariff, and proposed scope. Use the trial to inform the assumptions and revisit them where a property has different equipment or demand.
Choose the Next Sites for Boiler Optimisation
After the trial, ask each property for a short plant summary. Include the fuel type, the boilers involved, normal operating hours and the heating or hot water loads each serves. Record which gas readings can be tied to that plant and whether another heat source shares the duty. Note especially where upgrades are already funded, or equipment is due to be replaced. This gives the property director a way to compare sites by likely scope of work and available evidence.
Use the pilot to identify which sites are ready for the same assessment. Comparable boilers, operating hours and usable gas readings may support a similar measurement approach. At a club that shares a gas meter across several services, first establish what fuel use can be attributed to the proposed plant. Where the heating arrangement differs substantially from the pilot, start by assessing the installed equipment and the loads it serves.
Imagine two candidates after the pilot. One operates a similar pool and heating plant, but heating work is already due during the proposed comparison period. The other has a similar hot water load and stable operating hours, with gas readings available for the boilers in scope. The first may merit an early survey so the projects can be co-ordinated. The second may offer a clearer next comparison. The shortlist can accommodate both aims by stating why each site is being considered.
Record the next action for each candidate alongside the reason for shortlisting it. A property awaiting boiler replacement may need its own post-handover baseline. A site with stable plant and separate boiler metering may already be ready for a review of firing patterns. This record allows the property director to commission surveys in a sensible order and avoids leaving a promising property on the list indefinitely while the relevant condition changes.
Check local arrangements when scheduling the shortlist. A club may need to co-ordinate plant room access with a service visit or plan the work around pool and changing room use. Confirm that the local team is available to collect records for the review. Group candidate sites by the work they need and whether they are ready for the survey, monitoring and installation.
Make the Budget Traceable to Each Site
Give each candidate its own budget line. Show the boilers in scope, their estimated share of the gas meter total and the unit rate used to value the fuel savings. If the proposal includes insulation, record that measure and its cost as well. Two clubs with similar consumption can have different savings in pounds because of their tariffs and the reductions their systems are expected to achieve.
At an early stage, use a plausible range for each site and state what would move the estimate. Optiburner publishes typical commercial boiler fuel savings of 15–30%, dependent on conditions and fuel use. A successful first site helps the team assess further candidates, while the expected savings at any particular club depend on that club’s plant and operating profile. As the survey produces better information, replace broad assumptions with the details agreed for that property.
A staged budget can incorporate costs to assess and verify the work as well as to install it. Set a decision point after the next group of clubs, when the project team reviews installation experience and evidence quality alongside projected savings. The same measurement format can make results easier to compare across sites. Agree which records each club will supply so the person assessing the programme can interpret the figures without reconstructing the work from correspondence.
Give Every Phase a Review Date
Carry the unresolved questions from the pilot into the brief for the next sites. A reduction in firings on a boiler served by a shared meter may prompt the team to examine the available fuel data more closely. If demand records explain why two clubs behaved differently, use those records to decide when to gather data at the next group. Each phase can improve the evidence used for the next approval.
Check that the portfolio results keep common definitions. Record which periods underpin the savings, whether the number describes burner operation, fuel or utility costs, and which measures were installed. Use a common format for tariff assumptions, with each site’s own figure in the calculation. If testing was feasible at only some properties, show which results come from measured observations and which are estimates. This helps the estate team keep projections and results connected as the programme grows.
At the approval meeting, give the decision-maker a short account of the evidence that can be reused. It might cover which trend records were available, how long it took to obtain them and whether the test continued through typical opening hours. Add the assumptions that still need checking at each property. That distinction gives the director a basis for approving a group of surveys without treating those sites as though their fuel savings had already been measured.
Alongside energy performance, ask club staff what they learned about planning access, keeping plant available and gathering data. A repeatable way to organise those activities can be valuable when several projects are running at once. It also makes it easier to spot the sites that require a different approach. The next budget can then reflect the practical work involved and the estate's confidence in the fuel figures.
Use the Trial File to Plan the Next Sites
Bring the pilot findings, shortlisted sites and planned insulation work when you talk to Optiburner’s team about the rollout. The discussion can establish where the pilot is a useful comparison and what needs to be assessed afresh before you prepare a budget.
Run the Fuel Savings Calculator for each candidate with a usable boiler fuel baseline. Record the inputs against the site concerned. That gives the portfolio team a set of preliminary estimates it can refine as local surveys confirm the scope.