Work Out How Much Oil the Site Used
Start with a defined period, such as the last full year with reliable oil records. Collect the delivery dates, litres and prices, and look for a recorded tank level at each end of the period. Where opening and closing stock readings are reliable, and no oil has moved to or from another tank, add deliveries to opening stock and subtract closing stock. That is the volume drawn from the tank during the period. If you have transfers or other documented stock movements, include them in the reconciliation so the boiler estimate reflects the right fuel supply.
For example, take a site with 9,000 litres in stock at the start, 42,000 litres delivered during the year, and 11,000 litres left at the end. The implied draw from the tank is 40,000 litres. Using deliveries alone would add 2,000 litres to the baseline. If the tank readings are approximate, keep that uncertainty with the result. Where readings are missing, label delivery totals as a purchasing record and discuss what further information would support a consumption estimate.
Use the same method to record tank levels at both ends of the period and capture the dates of any deliveries close to those readings. A delivery booked on the last day of the month may arrive after the closing stock was recorded. Count it in the period in which it actually arrived. If the site records oil in several tanks, reconcile each relevant tank before combining the totals.
Confirm where that oil went. A tank serving only the boiler under review gives a clearer view of its fuel use. If the tank also supplies other equipment, look for metering or records that can support a credible split. The proposed saving applies to the fuel used by the boiler being assessed. The change in total tank use also depends on how the other equipment operates.
Find the dates that explain the larger movements in the records. A conference centre may close one accommodation block between bookings. A workshop may change its operating hours. A site with a separate source of summer hot water may use its oil boiler chiefly for space heating. A premises calendar beside the tank and delivery records helps the engineer understand the job the boiler was doing during the period you chose.
Put the Boiler and Burner on the Same Page
Collect the model details of both the boiler and the burner from the service record or plant schedule. Note which fuel the site uses, which heating and hot water services the plant supplies and what the records show about the existing controls. Optiburner gives forced draught and two-stage firing boilers as application examples. The assessment establishes whether the particular on-site combination is suitable.
On a dual-fuel installation, give each fuel its own line. Identify the periods when oil was actually used and what normally triggers a fuel change under the site’s operating arrangements. A boiler that uses oil only for occasional cover may have an entirely different oil-saving opportunity from an otherwise similar boiler running on oil for a whole heating season. Its wider fuel use can still be part of the site discussion, with each fuel reviewed against its own operating record and unit cost.
Follow the heat beyond the boiler. If the plant supplies space heating and hot water, describe when each service calls for heat and whether the same boiler serves both in summer. Where another boiler shares the work, add the operating periods for each unit if they are available. This helps an assessor interpret the fuel records and identify when the plant runs steadily and when it switches off and fires again. Ask the engineer to check how the available logs distinguish an instruction for the boiler to run from the burner actually firing.
Where an Oil Saving Would Come From
Heat stays in the boiler and the water circuit after the burner stops. Optiburner manages the timing of the next burn so the circuit can use that heat for longer where demand allows. The optimiser monitors the temperature of the water leaving the boiler so firing can resume when the system needs heat. With enough scope to lengthen the intervals between burns, the boiler may fire fewer times and spend less time burning across a comparable period.
Picture two periods in a single oil boiler’s working day. In the first, the building recovers from its overnight setback, and the burner runs for a sustained period. In the second, most rooms are at temperature, demand is lighter, and the burner restarts after shorter breaks. Ask when that second pattern occurs and how often it recurs. The opportunity depends on how the plant operates over its real schedule. A set of observations from one light-load afternoon gives the engineer a lead to follow, alongside evidence from busier days and other parts of the season.
Discuss which operating record can show the difference the optimiser makes. The product page describes comparing burner operation with optimisation engaged and disengaged and providing a downloadable Savings Report. That comparison can help explain a change in firing patterns. Assess the fuel outcome separately using the best consumption evidence available for the oil supply in scope. Where the burner can operate at different firing rates, burner minutes alone give a limited picture of litres used.
The two sources of evidence may be available on very different timescales. A burner trace can reveal a repeated pattern within a day. If the site relies on occasional tank readings, it may take longer to establish whether that pattern makes a material difference to annual consumption. Ask the assessor to explain what can be checked early and when the site can use its own records to attach a value to the change.
Agree a sensible review period and the information it needs to cover. With infrequent deliveries or coarse-level readings, a short test may show a change in burner operation before the tank record can show a meaningful change in fuel use. Establish how you would check that the premises received the same required heating and hot water during the comparison. A reliable assessment gives service delivery, burner evidence, and fuel records their place in the decision.
Ask how precisely the site can account for oil used over the proposed test period. If the recorded difference in tank levels is small compared with the uncertainty in those readings, extend the observation period or ask whether a better consumption record is available. That keeps the engineering observation useful while giving the fuel comparison enough data to support its own conclusion.
Price the Litres the Site Could Avoid
Use a unit price that reflects the site’s own oil purchases. Where the price varies by delivery, a volume-weighted average for comparable purchases can make the calculation easier to reproduce. For example, 8,000 litres at an illustrative 68 pence per litre and 12,000 litres at 74 pence per litre would cost £14,320 in total, averaging 71.6 pence per litre. Keep the tax basis clear and account separately for any fixed charges that would still apply. Use the expected price for a forward budget.
Suppose the boiler in scope accounted for all 40,000 litres in the earlier illustration. An assumed 10% reduction would save 4,000 litres under comparable operating conditions. At an assumed 71.6 pence per litre, the annual fuel-cost reduction would be £2,864. If the assessment found that only 30,000 litres went to the boiler, the same assumed reduction and price would give a saving of £2,148. These figures show how the calculation works. The reduction for a particular oil-fired boiler needs a site basis before finance puts it into the budget.
Carry the expected litres avoided and their value in pounds into the proposal. Finance can then update the price after a delivery quote changes while preserving the fuel assumption. Include any ongoing project costs on the same tax basis as the saving. If the annual net saving is positive, divide the upfront project cost by that figure to estimate simple payback in years.
For a site that buys oil in batches, a fuel saving can show up as more time between orders. The first delivery after a retrofit might arrive on the usual date because the premises manager already booked it. The financial benefit becomes apparent over the period in which the site needs to replace the oil it burns. Keep the savings forecast separate from the payment calendar where purchasing is seasonal. Finance can use the estimated annual litres to plan spending and the site’s own ordering policy to decide when those payments are likely to fall. This is especially useful when one delivery spans two budget periods.
If the estate has more than one delivery location, value each installation with the prices for its own supply where the records allow. That matters when a proposal covers a site with relatively low oil use and a depot with a much larger tank. Keeping the volumes visible makes it easier to see which boilers contribute most to the estimate.
There is also a useful check after installation. If the site orders fewer litres in the first winter, look at how much oil was in stock at the beginning and end before assigning a saving to the optimiser. Check whether the building had similar hours and heating needs. If oil costs more per litre than it did in the baseline year, the reduction in fuel use and the change in spending can move in different directions. Reporting both numbers makes the result more useful to the next person dealing with the fuel order or the budget.
Bring Your Oil and Burner Records to the Assessment
The most useful enquiry gives the engineer a clear starting point. Bring the boiler and burner models, a note of what the plant heats, and fuel records with dates and a description of what the tank serves. If the records cover several boilers or include periods on another fuel, say so at the outset. This gives the team a way to separate the potential savings on the proposed boiler from the changes that may come from how the site uses the rest of its plant.
Speak to the Optiburner team to review your oil-fired boiler, how its burner operates and the options for confirming savings on your fuel supply. Ask which oil consumption figures to use with the Optiburner Fuel Savings Calculator for an initial estimate. A reconciled set of tank and delivery records gives the team a clearer starting point for that calculation.